Phase 1
Assessment & Containment Design
Atlas reviews existing testing reports, confirms affected materials through independent sampling when needed, and designs the containment plan. This includes negative-air pressure calculations, decontamination unit placement, barrier wall construction specifications, and the work sequence that minimizes disruption to adjacent occupied spaces. We coordinate directly with your project manager, general contractor, or facility team to align the abatement schedule with the broader construction timeline.